Strong Mixed Concrete Sdn Bhd v ATSH Construction Sdn Bhd & Ors

Court of Appeal · · Contract Law

IMPORTANT DISCLAIMER: This digest provides AI-generated summaries of recent Malaysian legal judgments and is provided for general informational purposes only. The digest may contain errors, omissions, or inaccuracies, and does not constitute legal advice or a substitute for legal counsel. For complete and authoritative information, always consult a qualified legal professional and refer to official court sources (here) or the full text of original judgments. The providers of this digest accept no responsibility or liability for any loss and/or damage resulting from reliance on its contents.

Strong Mixed Concrete Sdn Bhd v ATSH Construction Sdn Bhd & Ors
CourtCourt of Appeal
Judgment Date23 November 2026
Date Uploaded25 November 2026
Legal TopicsContract Law
Parties

Appellant(s): Strong Mixed Concrete Sdn. Bhd.

Respondent(s):

  • Ssj Consulting Engineers Sdn Bhd
  • ATSH Construction Sdn Bhd
Bench
  • YA Datuk Mohamed Zaini Bin Mazlan
  • YA Dato' Faizah Binti Jamaludin
  • YA Datuk Dr Lim Hock Leng
Facts & Background
  • The appellant, a ready-mixed concrete (RMC) supplier, contracted with the main sub-contractor on a residential project to supply Grade 25 and Grade 30 concrete under a Concrete Mix Design agreement; independent core and chemical testing later revealed widespread under-strength concrete and insufficient cement content, leading to a stop-work order and eventual demolition of the partially built structure.
  • The sub-contractor sued the supplier for breach of contract and damages for defective RMC, while the supplier brought in the project's structural engineers as a Third Party and separately sued the sub-contractor and its director-guarantors for unpaid RMC deliveries; the High Court found the supplier liable and dismissed the Third Party claim and the supplier's own claim.
  • The supplier appealed both the liability finding and the quantum of special damages awarded (RM2,421,296.80), while the companion appeal concerning the unpaid RMC claim was accepted by the supplier to stand or fall with the outcome on liability in the main appeal.
Issues for the Court
  • Whether the "passing-of-risk" principle in RMC supply (that satisfactory cube tests at delivery discharge the supplier's obligations) precluded reliance on post-delivery coring and chemical test results to establish breach, and whether the trial judge erred in relying on such evidence absent specific pleading.
  • Whether the sub-contractor had proven actual loss under section 74 of the Contracts Act 1950 for its claimed special damages (materials, machinery, labour), given that it had received over RM2 million in progress payments from the main contractor for the same construction phase, raising concerns of double recovery.
  • Whether English common law doctrines (res inter alios acta and the "transferred loss" principle from The Albazero/Linden Gardens) could be invoked for the first time on appeal to justify recovery of expenditure, notwithstanding they were neither pleaded nor canvassed at trial, and whether they could override the compensatory scheme under section 74.
Decision
  • The Court affirmed the finding of liability against the supplier, holding that the "passing-of-risk" authorities were distinguishable since the contract also prescribed a minimum cement content (not met), and that evidential facts such as test results did not need to be separately pleaded as they supported the pleaded cause of action for supply of defective RMC.
  • The Court allowed the appeal in part on quantum, setting aside the awards for materials, machinery and labour (totalling over RM2.27 million) because the sub-contractor failed to reconcile this expenditure against the progress payments received for the same period, thereby failing to strictly prove actual loss under section 74 of the Contracts Act 1950; awards for post-stop-work testing and consultancy fees (RM148,098.30) were affirmed as these could not have been covered by the earlier progress payments.
  • The Court held that the belated reliance on English common law doctrines of transferred loss and res inter alios acta was impermissible as a new, unpleaded case on appeal, and in any event could not override the compensatory limits of section 74; costs below were reduced accordingly, and the companion appeal (for unpaid RMC deliveries and against the guarantors) was dismissed as it was contingent on the liability finding standing.
Link to JudgmentView Full Judgment