Ooi Choong Han v Glomac Segar Sdn Bhd

Court of Appeal · · Land & Property Law, Contract Law

IMPORTANT DISCLAIMER: This digest provides AI-generated summaries of recent Malaysian legal judgments and is provided for general informational purposes only. The digest may contain errors, omissions, or inaccuracies, and does not constitute legal advice or a substitute for legal counsel. For complete and authoritative information, always consult a qualified legal professional and refer to official court sources (here) or the full text of original judgments. The providers of this digest accept no responsibility or liability for any loss and/or damage resulting from reliance on its contents.

Ooi Choong Han v Glomac Segar Sdn Bhd
CourtCourt of Appeal
Judgment Date22 October 2026
Date Uploaded26 October 2026
Legal TopicsLand & Property Law, Contract Law
Parties

Appellant(s): Ooi Choong Han

Respondent(s): Glomac Segar Sdn. Bhd.

Bench
  • YA Dato' Azizul Azmi Bin Adnan
  • YA Dato' Ong Chee Kwan
  • YA Dato' Nadzarin Bin Wok Nordin
Facts & Background
  • The purchaser bought a unit from the developer under a Schedule H sale and purchase agreement which provided for delivery of vacant possession within 48 months instead of the statutory 36 months.
  • The developer relied on a letter dated 29.6.2018, signed by the Deputy Controller of Housing in his own name (not "for and on behalf of" the Controller), to justify the extended period; no written delegation from the Controller was ever produced.
  • After deducting pandemic-related exclusion periods, vacant possession was still delivered more than a year late, prompting the purchaser's claim for liquidated ascertained damages (LAD), which was dismissed by the Magistrate Court and the High Court on appeal.
Issues for the Court
  • Whether a Deputy Controller of Housing has power under regulation 11(3) of the Housing Development Regulations to grant an extension of time in his own right, or only pursuant to a written delegation under section 4(3) of the Housing Development Act.
  • Whether the purchaser was required to challenge the validity of the Deputy Controller's letter by way of judicial review before relying on its invalidity as a defence to the developer's reliance on the extended period.
  • Whether the Federal Court's "second actor theory" in Obata-Ambak, or the principle that a signed contract binds the parties, could validate or preserve the 48-month term despite the absence of proof that the extension was granted by the Controller or his lawful delegate.
Decision
  • The Court held that a Deputy Controller has no power in his own right under regulation 11(3) to grant extensions; such power may only be exercised pursuant to a written delegation under section 4(3) of the Act, and since none was proved, the letter was made without power and granted no valid extension.
  • The Court held that judicial review was not required because the claim was a private law claim to enforce contractual/statutory rights to LAD, and a decision made wholly without power is void and may be challenged collaterally in ordinary proceedings; this was distinguished from Obata-Ambak, where the extension had been validly granted by the Controller before being affected by the prospective-only ruling in Ang Ming Lee.
  • The Court found that neither the second actor theory nor the principle that signed contracts bind parties could validate the extension, as these doctrines presuppose a genuine (even if later invalidated) exercise of power; the appeal was allowed, with the statutory 36-month period applying, and damages recalculated (incorporating a further 153-day exclusion under the COVID-19 Act) to RM45,786.30 for late vacant possession and RM14,903.44 for late completion of common facilities, plus interest and costs.
Link to JudgmentView Full Judgment