Dayanam Constructions Sdn Bhd v THP Enstek Development Sdn Bhd

Court of Appeal · · Contract Law

IMPORTANT DISCLAIMER: This digest provides AI-generated summaries of recent Malaysian legal judgments and is provided for general informational purposes only. The digest may contain errors, omissions, or inaccuracies, and does not constitute legal advice or a substitute for legal counsel. For complete and authoritative information, always consult a qualified legal professional and refer to official court sources (here) or the full text of original judgments. The providers of this digest accept no responsibility or liability for any loss and/or damage resulting from reliance on its contents.

Dayanam Constructions Sdn Bhd v THP Enstek Development Sdn Bhd
CourtCourt of Appeal
Judgment Date19 October 2026
Date Uploaded20 November 2026
Legal TopicsContract Law
Parties

Appellant(s): Davanam Constructions Sdn Bhd

Respondent(s): THP ENSTEK DEVELOPMENT SDN BHD (Formerly known as

Bench
  • YA Datuk Azhahari Kamal bin Ramli
  • YA Dato' Nadzarin Bin Wok Nordin
  • YA Tuan Muniandy a/l Kannyappan
Facts & Background
  • The developer and a construction company entered into a series of agreements, including a Framework Agreement and a Joint Venture Development Agreement (JVDA), under which the construction company (via assignment from an intermediate SPV) was to plan, finance and construct an iconic ultra-low density luxury villa and clubhouse development ("Chedi" branded) on land owned by the developer.
  • After an Approved Master Plan was obtained in 2010, the project stalled with no physical construction, and the construction company later proposed a radically different, higher-density mass-market development ("Waterford @ Enstek"), allegedly due to its inability to secure financing.
  • The developer terminated the JVDA in 2016 for breach and forfeited a RM2 million deposit, prompting the construction company to sue for wrongful termination and specific performance/damages (claiming up to RM1.4 billion), while the developer counterclaimed for loss of its entitlement under the agreements.
Issues for the Court
  • Whether the construction company had unilaterally and unlawfully departed from the Approved Master Plan and committed a fundamental/repudiatory breach of the JVDA entitling the developer to terminate.
  • Whether clause 16.5 of the JVDA (permitting amendment of the Development Plan) could be read in isolation to give the construction company an unconditional right to amend the Approved Master Plan, or whether it was conditional on non-approval by authorities and had to be construed with the agreement as a whole.
  • Whether the developer's termination notice complied with the multi-step notice-and-remedy procedure under clause 17.1(i) of the JVDA, and whether this point (raised for the first time on appeal) could be entertained as a question of law.
  • Whether mutual delays and acquiescence by both parties in respect of ancillary breaches gave rise to estoppel, barring either party from relying on such breaches.
Decision
  • The Court of Appeal held that all the related agreements (MOU, LOI, Framework Agreement, JVDA, Addendum Agreement, Assignment Agreement) must be read conjunctively, and on that basis the construction company was contractually bound to develop the iconic Chedi-branded project per the Approved Master Plan, with no unilateral right to depart from it absent authority non-approval.
  • The Court found that the construction company was financially incapable of performing its obligations and had committed a fundamental/repudiatory breach by abandoning the Approved Master Plan for a materially different mass-market development, entitling the developer to terminate the JVDA; the new "notice procedure" argument was rejected as a mixed question of law and fact not properly raised below.
  • Both parties were estopped from raising ancillary/technical breaches due to mutual delay and acquiescence over many years; accordingly, both the construction company's appeal (claim for damages/specific performance) and the developer's appeal (counterclaim for loss of entitlement) were dismissed, affirming the High Court's decision with costs of RM50,000 awarded to each respondent.
Link to JudgmentView Full Judgment