Encorp Iskandar Development Sdn Bhd v Teo Choon Poh & Ors

Court of Appeal · · Contract Law, Land & Property Law

IMPORTANT DISCLAIMER: This digest provides AI-generated summaries of recent Malaysian legal judgments and is provided for general informational purposes only. The digest may contain errors, omissions, or inaccuracies, and does not constitute legal advice or a substitute for legal counsel. For complete and authoritative information, always consult a qualified legal professional and refer to official court sources (here) or the full text of original judgments. The providers of this digest accept no responsibility or liability for any loss and/or damage resulting from reliance on its contents.

Encorp Iskandar Development Sdn Bhd v Teo Choon Poh & Ors
CourtCourt of Appeal
Judgment Date27 August 2025
Date Uploaded4 September 2025
Legal TopicsContract Law, Land & Property Law
Parties

Appellant(s): Encorp Iskandar Development Sdn Bhd

Respondent(s): Xxxx

Bench
  • YA Dato' Hashim Bin Hamzah
  • YA Datuk Azimah binti Omar
  • YA Datuk Ismail Bin Brahim
Facts & Background
  • The appellant, a developer, offered a Developer's Interest-Bearing Scheme (DIBS) to purchasers of a strata project, undertaking to bear progressive loan interests during the "construction period".
  • The Sale and Purchase Agreements (SPAs) stipulated a 48-month period for vacant possession (Contract Period), but the DIBS Agreement was ambiguously drafted regarding the duration of the "construction period".
  • The appellant failed to deliver vacant possession within the 48-month Contract Period, continued to pay interest for a period beyond it, but later demanded reimbursement from the purchasers, arguing the DIBS period was limited to 48 months.
Issues for the Court
  • Whether the "construction period" under the Developer's Interest-Bearing Scheme (DIBS) was limited to the 48-month contractual period for vacant possession or extended until the actual delivery of vacant possession, including delays.
  • Whether the *contra preferentum* rule should apply against the appellant due to the ambiguity in the DIBS Agreement drafted by them.
  • Whether the subsequent conduct of the parties and the equitable doctrine of estoppel were relevant in interpreting the contractual terms and determining liability.
Decision
  • The Court affirmed the High Court's decision, ruling that the appellant was contractually obligated to bear progressive interest under the DIBS scheme until the actual delivery of vacant possession, including periods of delay beyond the 48-month Contract Period.
  • The Court applied the *contra preferentum* rule against the appellant due to the ambiguous drafting of the DIBS Agreement and considered contemporaneous documentary evidence and the appellant's own subsequent conduct of continuing payments.
  • The Court held that estoppel applied in favour of the purchasers, as the appellant's earlier voluntary payments contradicted its later demand for reimbursement, which was made under circumstances of inequity and coercion against the purchasers.
Link to JudgmentView Full Judgment

Related judgments

📬 Found this useful?

Get daily AI-generated summaries of Malaysian legal judgments from the Federal Court and the Court of Appeal straight to your inbox, free!